    Pacific Highway - Wells Crossing to Glenugie Section 2A

    The Wells Crossing to Glenugie Section 2A project involves construction of 8km of new northbound only carriageway to median-separated dual-carriageway and is particularly significant as it represents the final component of the W2B section of the Pacific Highway. Our scope includes clearing and grubbing, earthworks, drainage, plain concrete pavement, fauna crossings, road furniture, delineation and landscaping for two northbound lanes in a single carriageway.

    In August 2019 Roads & Maritime Services (now Transport for NSW) directly awarded ACCIONA a contract for the Early Works for the final 8km Section 2A of the W2B roadworks from Wells Crossing to Glenugie, followed by award of the main contract in February 2020. This was our fifth successful tender on the overall Pacific Highway W2B Upgrade. Factors contributing to our win included the timely delivery and safety achievements of our highly experienced teams on W2B Sections 10&11 and the Richmond River Bridge project. Our scope includes clearing and grubbing, earthworks, drainage, plain concrete pavement, fauna crossings, road furniture, delineation and landscaping for two northbound lanes in a single carriageway.

    Early Works commenced in August 2019 and overall completion is scheduled for July 2021. Interestingly, our project team measured what is believed to be a new record of wet weather for our projects, recording more than 1018mm of rainfall in a single month in mid-February 2020.

    Following the success of our trial use of recycled glass in the paving of the W2B Sections 10 & 11 project, we will work collaboratively with RMS and Lismore Council to continue that initiative on this project.

    Other components of the W2B project included the Sections 10 & 11 Civil Works, Section 10 Pavement and the Bridge over Richmond River at Broadwater. In addition, our sister company Australian Precast Solutions supplied all Precast Planks, Headstocks and Abutments for all 155 bridges in the entire Woolgoolga to Ballina Upgrade.

    This project adds to our strong track record in having upgraded more than 289km of the Pacific Highway’s 669km between Hexham and Tweed Heads.

    General information

    Location: Pacific Highway, Wells Crossing to Glenugie, NSW

    Contract Type: Construct only

    Completion date: August 2019 – May 2021 (forecast)

    Project Value: $69.4 million

    key Features

    • Length: 8km
    • Earthworks: 320,000m3
    • 8 x Structural Culverts + 1 Bebo Archway

    Benefits

    • Improved road user safety for the 8km of NB carriage way between Wells crossing to Glenugie though upgraded road alignment/geometry
    • Improved pavement quality and upgraded safety barrier systems
    • Upgraded and safer intersections and access to adjoining local roads though acceleration and deceleration lanes and uturn bays
    • Upgraded fauna connectivity through the NB carriage way and exclusion fencing from the old NB Pacific Highway all resulting in continuity with the remainder of the Woolgoolga to Ballina upgrades to the North and South.

    Environmental information

    Environmental Protection Licence 21330

    Location of Monitoring Points 21330

    Pollution Incident Response Management Summary 21330

    Environmental Protection Licence Monitoring Data:

    Image Gallery

    discover other flagship projects

    Toowoomba Second Range Crossing

    Toowoomba, QLD (Australia)

    ACCIONA, as a Design and Construct JV partner of the Nexus Infrastructure consortium, ACCIONA was awarded the contract to design and construct the $1.6 billion Toowoomba Second Range Crossing (TSRC). 

    Bridge over Clarence River at Harwood

    Harwood, NSW (Australia)

    ACCIONA as part of Acciona Ferrovial Joint Venture (AFJV), was engaged to design and build the new bridge over the Clarence River at Harwood, located on the Pacific Highway, in New South Wales.

    Move up

    YOU'RE JUST ONE STEP AWAY!

    Please, confirm your subscription on the email we have sent you and your registration will be completed.

    YOU'VE ONLY GOT ONE STEP LEFT!

    Please confirm your subscription in the email we just sent you to complete the registration and you will be able to download your ebook.

    YOU ARE ALREADY SUBSCRIBED TO THE NEWSLETTER!

    If you've missed our content, try checking your junk mailbox and
    add us to your address book so you can enjoy them without any problem.

    An error has occurred.

    Your email has been unsubscribed. You will not receive more newsletters, unless you subscribe again. Thank you very much