Innovation Partnerships Awards Corporate Governance Energy Transport Water Social Cities Real estate Financial Projects

The proyect, located on the northwestern of Spain, counts with 21 km highway.

This 21 km highway has two carriageways, each with two lanes, a 2.5 -m hard shoulder, 16 underpasses, 14 overpasses with 4 pull-out bays with a total length of 58 m. The project was completed in March 2007.

As singular elements, the following stand out:

  • 2 double-deck viaducts, the first 128 m long and the second 356 m long.
  • 2 overpasses over the N-VI road and one over the Palencia - A Coruña railway line.
  • 16 subways and 14 overpasses.

GENERAL INFORMATION

  • Location: O Corgo, Lancara and Baralla, Lugo, Spain.
  • Contract type: Construction.
  • Infrastructure: Two carriageways of two lanes, each with a length of 20.7 km, 2 viaducts, 2 wildlife overpasses, 16 underpasses and 14 overpasses.
  • Year of project completion: 2007